We will post the latest notices of Exposition Line Phase 2 construction on this page. Read the latest on Expo Phase II in the Summer Quarter 2012 Expo E-News.
***Posted June 11, 2013
What: Venice Boulevard Median Reconstruction for Street Widening
When: Sunday, June 23, 2013 through Friday, August 9, 2013
| Work Activity | Duration | Hours |
| Installation of Temporary Traffic Control and Striping for Removal of Street Parking on the South Side of Venice Boulevard | June 23, 2013 (1 night only) | 9:00 p.m. – 6:00 a.m. |
| Median Reconstruction | June 24, 2013 – August 9, 2013 | 9:00 p.m. – 6:00 a.m. |
Work Description:
Construction of the Venice Boulevard Bridge, with columns in the center of the street, will require the widening of Venice Boulevard which includes the reconstruction of the median and reconfiguration of traffic lanes. Initial activities will include the removal of a few trees located in the median and on the north side of Venice Boulevard, as well as the removal of existing light poles and the installation of temporary lighting on the north and south sides of Venice Boulevard between Robertson Boulevard and Ivy Street. Both of these activities will take place between June 12 – June 20.
Median reconstruction will entail saw cutting and removal of the existing asphalt and concrete median, followed by the construction of a new median to accommodate the future reconfiguration of traffic lanes on Westbound Venice Boulevard. The parking lane along Eastbound Venice Boulevard, from Robertson Boulevard to Ivy Street, will be temporarily converted to a traffic lane and street parking will be prohibited during the duration of the work.
Traffic Impacts:
- Intermittent traffic lane impacts on Southbound and Westbound Venice Boulevard will be implemented during nighttime hours during the tree removal and the temporary lighting installation.
- Westbound Venice Boulevard from National Boulevard to Robertson Boulevard will be reduced to one traffic lane during nighttime hours.
- Westbound and Eastbound Venice Blvd from Ivy Street to National Blvd will be intermittently reduced to two traffic lanes during nighttime hours.
Advisories:
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Directional signage will be used to safely direct drivers and pedestrians around the construction zones.
- Local and pedestrian access will be maintained at all times.
- Please do not enter the construction work zone and obey all posted construction signs.
(Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.)
***Posted May 23, 2013
What: Lane Closures for Retaining Wall Construction
When: Tuesday, May 28, 2013 through Friday, August 2, 2013
Work Hours: 9:00 a.m. to 3:30 p.m., Monday through Friday
Where: Construction activities will take place on the Expo ROW at National Boulevard between Palms Boulevard and Clarington Avenue
Work Description:
Retaining wall construction activities will include the use of a crane to complete the wall installation. Due to space constraints, a crane will sit on the westbound lanes of National Boulevard in order to complete the installation of the wall.
Traffic Impacts:
- Westbound National Boulevard between Palms Boulevard and Clarington Avenue will be closed to all through traffic and all turns onto westbound National Boulevard will be prohibited.
- Traffic heading westbound on National Boulevard will be directed to continue westbound on Palms Boulevard.
- Eastbound National Boulevard will remain open and monitored by flaggers between Clarington Avenue and Palms Boulevard.
- Turn restrictions will be implemented in this area during work hours, please obey all posted traffic signs.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
- Electronic message boards, directional signage and/or flaggers will be used to maintain traffic flow and safely direct vehicles and pedestrians around the construction zone.
Advisories:
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
***Posted May 23, 2013
What: Closure of Robertson Boulevard and Venice Boulevard for Falsework Installation for Bridge Construction
Work Hours: Sunday to Thursday: 9:00 p.m. to 6:00 a.m.
Friday: 12:00 a.m. (Midnight) to 8:00 a.m. (Occasional if needed)
| Location of Closure | Duration |
| Closure of Robertson Blvd between Hoke Avenue and Venice Boulevard | Sunday, June 2, 2013 – Tuesday, June 11, 2013 |
| Closure of Eastbound Venice Boulevard between Culver Boulevard and Robertson Boulevard* Occasional closures of Robertson Boulevard between Hoke Avenue and Venice Boulevard will be required during this period, but will not occur concurrently with the Venice Boulevard closures | Wednesday, June 12, 2013 – Friday, June 21, 2013 |
| Closure of Westbound Venice Boulevard between Robertson Boulevard and Culver Boulevard | Sunday, June 23, 2013 – Wednesday, July 31, 2013 |
Work Description:
Construction crews will erect falsework using timber and steel forms as a mold for the cast-in-place concrete bridge that will span Robertson Boulevard and Venice Boulevard.
Traffic Impacts During the Closures of Robertson Boulevard:
- Robertson Boulevard will be closed between Hoke Avenue and Venice Boulevard, and traffic will be detoured at Washington Boulevard and National Boulevards.
Traffic Impacts During Closures of Eastbound Venice Boulevard:
- Eastbound Venice Boulevard will be closed to through traffic from Culver Boulevard to Robertson Boulevard, and traffic will be detoured at Bagley Avenue/Main Street or Culver Boulevard.
- Right turns on to eastbound Venice Boulevard from Culver Boulevard will be prohibited, and traffic will be detoured to Washington Boulevard at InceBoulevard.
- Eastbound Venice Boulevard between Watseka Avenue and Culver Boulevard will be reduced to one lane of traffic.
Traffic Impacts During Closures of Westbound Venice Boulevard:
- Westbound Venice Boulevard will be closed to through traffic from Robertson Boulevard to Culver Boulevard, and traffic will be detoured at National Boulevard.
- Right turns from the eastbound I-10 Freeway Robertson Boulevard off ramp onto westbound Venice Boulevard will be prohibited.
- Through traffic and left turns across Venice Boulevard will be prohibited. All traffic will be detoured to north Robertson Boulevard or eastbound Venice Boulevard.
- Westbound Venice Boulevard between Ellis Avenue and Robertson Boulevard will be reduced to one lane of traffic.
Advisories:
- Pedestrian access will be maintained at all times or via designated walkway installed by the contractor.
- Local access to businesses will be maintained.
- Directional signage and electronic message boards will advise of the detours during the closures.
For an updated calendar of scheduled work activities, please visit www.ExpoVenice.org
***Posted April 24, 2013
What: Street Restoration and Paving
Where: Construction activities will take place on National, Palms and Exposition Boulevards
Work Hours and Duration:
| Location | Work Hours |
|
Saturday, April 27, 20138:00 a.m. to 6:00 p.m. |
|
Monday, April 29 or Tuesday, April 30, 20139:00 a.m. to 3:30 p.m. |
|
Monday, April 29 or Tuesday, April 30, 20139:00 a.m. to 3:30 p.m. |
Traffic Impacts:
- The intersection of National Boulevard and Palms Boulevard will be closed to all through traffic during the Saturday closure, and traffic will be detoured as follows
- Eastbound traffic on National Boulevard will be detoured at Motor Avenue
- Northbound traffic on Palms Boulevard will be detoured at Motor Avenue
- Westbound traffic on National Boulevard will be detoured at Bagley Avenue
- Westbound National Boulevard will be closed between Palms Boulevard and Clarington Avenue and all turns onto westbound National Boulevard will be prohibited. Eastbound National Boulevard will remain open, but will be detoured at the intersection.
- Exposition Boulevard between Palms Boulevard and Tabor Street will be closed to all through traffic. Westbound traffic will be detoured at Tabor Street and eastbound traffic will be detoured at Palms Boulevard.
- Palms Boulevard will be reduced to one lane of traffic in each direction between National Boulevard and Clarington Avenue. Turns throughout the work area will be prohibited.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
- Electronic message boards, directional signage and/or flaggers will be used to maintain traffic flow and safely direct vehicles and pedestrians around the construction zone.
Advisories:
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
***Posted April 18, 2013
|
What: Full Closure of National Boulevard for Falsework Removal
When: Monday, April 29, 2013 through Friday, June 1, 2013 (Work will take place approximately two weeks within the timeframe provided)
Work Hours: 9:00 p.m. to 6:00 a.m. Monday through Friday (Night work only)
Where: Construction activities will be located on National Boulevard north of the intersection of National/Palms Boulevards
Work Description:
Construction crews will remove falsework used as a mold for the cast-in-place concrete bridge that will span over National Boulevard.
Traffic Impacts:
- National Boulevard will be closed to all traffic between Manning Avenue and Exposition Boulevard throughout the falsework removal during nighttime hours.
- Westbound National Boulevard traffic will be detoured at Bagley Avenue.
- Northbound Palms Boulevard traffic will be detoured at Exposition Boulevard.
- All traffic lanes will be open to through traffic during daytime hours.
- Electronic message boards will be used to advise of the closures and manage traffic detours to update commuters as necessary.
- Directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
Advisories:
- Local access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
(Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.)
To view the construction notice – please click here.
***Posted April 16, 2013
What: Motor Avenue Bridge Construction
Where: Construction activities will take place on the Expo ROW and Motor Avenue, just north of Irene Street
When: Work Activities are scheduled as follows:
| Site Preparation | Monday, April 29 – Friday, May 3, 2013 (Day Work) – 9:00 a.m. to 3:30 p.m. |
| Restriping of Traffic Lanes and K-Rail (Concrete Barrier) Installation | Monday, May 6 – Friday, May 10, 2013 (Night Work) 9:00 p.m. to 6:00 a.m. |
| Bridge Construction Begins | Monday, May 6 (Day Work 7:00 a.m. to 6:00 p.m.- Approximately 6-8 months) |
Work Description:
Construction of the Motor Avenue Bridge will require the realignment and restriping of traffic lanes along Motor Avenue between National Boulevard and Walavista Road. K-rail (concrete barriers) will be placed on Motor Avenue to delineate new traffic lane boundaries and to protect work crews. Due to placement of K-rail, parking on the west side of Motor Avenue under the I-10 Freeway will be prohibited throughout the bridge construction. Most construction activities will be limited to areas behind the K-rail and the Expo ROW.
Traffic Impacts:
- Northbound and southbound Motor Avenue will remain open to through traffic. However, the center turn lane will be eliminated and one lane in each direction between National Boulevard and Walavista Road will be maintained during these construction activities.
- Electronic message boards, directional signage and/or flagmen will be used to safely to safely direct vehicles and pedestrians around the construction zone.
- Pedestrian access will be maintained and directional signage will be in place as needed.
Advisories:
- Supplemental notices will be provided for additional night work activities.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
- Local access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
(Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.)
***Posted April 15, 2013
What: Intermittent Closures of Venice Boulevard for Pile and Column Installation for the Venice Boulevard Bridge
Where: Construction will take place on Venice Boulevard, west of Robertson Boulevard
When: Sunday, April 21, 2013 through Sunday, May 21, 2013
Work Hours: Sunday to Thursday: 9:00 p.m. to 6:00 a.m.
Friday: 12:00 a.m. (Midnight) to 8:00 a.m.
Work Description:
Work crews will be drilling, setting, and forming column foundations for the Venice Boulevard Bridge. Overnight, intermittent closures of eastbound and westbound Venice Boulevard, between Culver Boulevard and Robertson Boulevard, will be required. Closures will not be implemented concurrently. To view an updated schedule of closures, please visit www.ExpoVenice.org
Traffic Impacts During Closures of Eastbound Venice Boulevard:
- Eastbound Venice Boulevard will be closed to through traffic from Culver Boulevard to Robertson Boulevard, and traffic will be detoured at Bagley Avenue/Main Street or Culver Boulevard.
- Right turns from Culver Boulevard to eastbound Venice Boulevard will be prohibited, and traffic will be detoured to Washington Boulevard at Ince Boulevard.
- Eastbound Venice Boulevard between Watseka Avenue and Culver Boulevard will be reduced to one lane of traffic.
Traffic Impacts During Closures of Westbound Venice Boulevard:
- Westbound Venice Boulevard will be closed to through traffic from Robertson Boulevard to Culver Boulevard, and traffic will be detoured at National Boulevard.
- Right turns from the eastbound I-10 Freeway Robertson Boulevard off ramp onto westbound Venice Boulevard will be prohibited.
- Left turns from northbound Robertson Boulevard to westbound Venice Boulevard will be prohibited.
- Westbound Venice Boulevard between Ellis Avenue and Robertson Boulevard will be reduced to one lane of traffic.
Advisories:
- Pedestrian access will be maintained at all times or via designated walkway installed by the contractor.
- Noise levels will be monitored to ensure compliance and the work area will be watered down to minimize dust.
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Local access to businesses will be maintained.
- Directional signage and electronic message boards will advise of the detours during the closures
- Please obey all posted construction signs and do not enter the construction work zone.
For an updated calendar of scheduled work activities, please visit www.ExpoVenice.org
(Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.)
***Posted April 12, 2013
As part of the construction of Phase 2 of the Expo Light Rail Line, work crews will begin all the necessary activities to support the construction of the Motor Avenue Bridge, including implementation of new traffic controls, excavation for the bridge foundations and construction of the bridge structure on the Expo Right-of-Way (ROW) in the City of Los Angeles. The work is being managed and performed by the Expo Phase 2 design-build contractor Skanska-Rados, Joint Venture (SRJV) and its subcontractors.
What: Motor Avenue Bridge Construction
Where: Construction will take place on the Expo ROW and Motor Avenue, just north of Irene Street
When: Work activities are scheduled as follows: Note: Additional night work will be required for the installation and removal of the bridge falsework. Work is anticipated to take place in August and September 2013. Each activity is expected to take approximately 2 weeks.
| Site Preparation | Monday, April 29 – Friday, May 3, 2013 (Day Work) – 9:00 a.m. to 3:30 p.m. |
| Restriping Traffic Lanes and K-rail (Concrete Barrier) Installation | Monday, May 6 – Friday, May 10, 2013 (Night Work) – 9:00 p.m. to 6:00 a.m. |
| Bridge Construction Begins | Monday, May 6 (Day Work) – 7:00 a.m. to 6:00 p.m. – Approximately 6-8 months |
Work Description:
Construction of the Motor Avenue Bridge will require the realignment and restriping of traffic lanes along Motor Avenue between National Boulevard and Walavista Road. K-rail (concrete barriers) will be placed on Motor Avenue to delineate new traffic lane boundaries and to protect work crews. Due to placement of K-rail, parking on the west side of Motor Avenue under the I-10 Freeway will be prohibited throughout the bridge construction. Most construction activities will be limited to areas behind the K-rail and the Expo ROW.
Traffic Impacts:
- Northbound and southbound Motor Avenue will remain open to through traffic. However, the center turn lane will be eliminated and one lane in each direction will be maintained between National Boulevard and Walavista Road.
- Electronic message boards, directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
- Pedestrian access will be maintained and directional signage will be in place as needed.
Advisories:
- Supplemental notices will be provided for additional night work activities.
- Local access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
***Posted April 12, 2013
What: Intermittent Closures of Venice Boulevard for Pile and Column Installation for the Venice Boulevard Bridge
Where: Construction will take place on Venice Boulevard, west of Robertson Boulevard
When: Sunday, April 21, 2013 through Sunday, May 21, 2013
Work Hours: Sunday to Thursday: 9:00 p.m. to 6:00 a.m.
Friday: 12:00 a.m. (Midnight) to 8:00 a.m.
Work Description:
Work crews will be drilling, setting, and forming column foundations for the Venice Boulevard Bridge. Overnight, intermittent closures of eastbound and westbound Venice Boulevard, between Culver Boulevard and Robertson Boulevard, will be required. Closures will not be implemented concurrently. To view an updated schedule of closures, please visit www.ExpoVenice.org
Traffic Impacts During Closures of Eastbound Venice Boulevard:
- Eastbound Venice Boulevard will be closed to through traffic from Culver Boulevard to Robertson Boulevard, and traffic will be detoured at Bagley Avenue/Main Street or Culver Boulevard.
- Right turns from Culver Boulevard to eastbound Venice Boulevard will be prohibited, and traffic will be detoured to Washington Boulevard at Ince Boulevard.
- Eastbound Venice Boulevard between Watseka Avenue and Culver Boulevard will be reduced to one lane of traffic.
Traffic Impacts During Closures of Westbound Venice Boulevard:
- Westbound Venice Boulevard will be closed to through traffic from Robertson Boulevard to Culver Boulevard, and traffic will be detoured at National Boulevard.
- Right turns from the eastbound I-10 Freeway Robertson Boulevard off ramp onto westbound Venice Boulevard will be prohibited.
- Left turns from northbound Robertson Boulevard to westbound Venice Boulevard will be prohibited.
- Westbound Venice Boulevard between Ellis Avenue and Robertson Boulevard will be reduced to one lane of traffic.
Advisories:
- Pedestrian access will be maintained at all times or via designated walkway installed by the contractor.
- Noise levels will be monitored to ensure compliance and the work area will be watered down to minimize dust.
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Local access to businesses will be maintained.
- Directional signage and electronic message boards will advise of the detours during the closures
- Please obey all posted construction signs and do not enter the construction work zone.
For an updated calendar of scheduled work activities, please visit www.ExpoVenice.org
(Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.)
***Posted March 30, 2013
What: Pile and Column Installation for the Venice Boulevard Bridge
Where: Construction will take place on Robertson Boulevard, south of Venice Boulevard
When: Monday, April 1, 2013 through Thursday, May 2, 2013
Work Hours: 9:00 p.m. to 6:00 a.m., Sunday through Thursday
Friday: 12:00 a.m. (Midnight) to 8:00 a.m.
Work Description:
Work crews will be drilling, setting, and forming column foundations for the Venice Boulevard Bridge
Traffic Impacts:
- Northbound Robertson Boulevard south of Venice Boulevard will be reduced to one lane.
- Southbound Robertson Boulevard will remain open.
- During this time, there will be full closures of Robertson Boulevard between Venice Boulevard and HokeAvenue. Closures will only be implemented when necessary. For an updated schedule of closures, please visitwww.ExpoVenice.org
- During these closures, traffic will be detoured as follows:
> Northbound traffic on Robertson Boulevard will be detoured at Washington Boulevard.
> Eastbound traffic on Venice Boulevard turning right onto southbound Robertson Boulevard will be detoured to National Boulevard.
> Local access to Robertson Boulevard between Washington Boulevard and Hoke Avenue will be maintained via flaggers.
- Directional signage and electronic message boards will advise of detours during the closures.
Advisories:
- Noise levels will be monitored to ensure compliance and the work area will be watered down to minimize dust.
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Local access to businesses will be maintained.
- Electronic message boards and directional signage will be used to safely direct drivers and pedestrians around the construction zones.
- Please obey all posted construction signs and do not enter the construction work zone.
***Posted March 2, 2013
When: Monday, March 11, 2013 through Wednesday, March 13, 2013
Work Hours: 9:00 p.m. to 5:00 a.m.
Where: Robertson Boulevard between Venice Boulevard and Hoke Avenue
Work Description:
Work crews will temporarily close Robertson Boulevard for the removal of two trees and installation of fencing and K-rail required for bridge construction. Work activities will include tree removal and stump grinding.
Traffic Impacts:
- Robertson Boulevard will be closed between Venice Boulevard and Hoke Avenue.
- Northbound traffic on Robertson Boulevard will be detoured at Washington Boulevard to National Boulevard.
- Eastbound traffic on Venice Boulevard turning right onto southbound Robertson Boulevard will be detoured to National Boulevard.
- Westbound traffic on Venice Boulevard turning left onto southbound Robertson Boulevard will be detoured to Culver Boulevard.
- Local access to northbound Robertson Boulevard between Washington Boulevard and Hoke Avenue will be maintained by flaggers.
Advisories:
- Noise levels will be monitored to ensure work is performed within the necessary compliance levels.
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Please do not enter the construction work zone and obey all posted construction signs.
- Electronic message boards and directional signage will be used to safely direct drivers and pedestrians around the construction zones.
- Local access to all businesses will be maintained
(Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.)
To view the construction notice – please click here.
***Posted February 1, 2013
National/Palms Bridge Construction – Night Intersection Closure for Falsework Installation
Please find enclosed our supplemental construction notice regarding the temporary night closure of National Boulevard between Manning Avenue and Exposition Boulevard for falsework installation for the National/Palms Bridge in the City of Los Angeles.
What: Full Closure of National Boulevard for Falsework Installation for Bridge Construction
When: Monday, February 11, 2013 through Friday, February 22, 2013
Work Hours: 9:00 p.m. to 6:00 a.m. Monday through Friday (Night work only)
Where: Construction activities will be located on National Boulevard north of the intersection of National/Palms Boulevards
Work Description:
Construction crews will erect falsework using timber and steel forms as a mold for the cast-in-place concrete bridge that will span over National Boulevard.
Traffic Impacts:
- National Boulevard will be closed to all traffic between Manning Avenue and Exposition Boulevard throughout the falsework installation during nighttime hours.
- Westbound National Boulevard traffic will be detoured at Bagley Avenue.
- Northbound Palms Boulevard traffic will be detoured at Exposition Boulevard.
- All traffic lanes will be open to through traffic during daytime hours.
- Electronic message boards will be used to advise of the closures and manage traffic detours to update commuters as necessary.
- Directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
Advisories:
- Local access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
****Posted February 1, 2013
Please find enclosed an updated construction notice regarding the night closure of Robertson Boulevard for the installation of a temporary drainage line.
When: Thursday, February 7, 2013 and Saturday, February 9, 2013
Work Hours: 9:00 p.m. to 5:00 a.m., Thursday
12:00 a.m. to 8:00 a.m., Saturday (If Necessary)
Where: Robertson Boulevard between Venice Boulevard and Hoke Avenue
Work Description:
Work crews will temporarily close Robertson Boulevard for the installation of a temporary drainage line required for bridge construction. Work activities will include saw-cutting and removal of asphalt, excavation of soil, installation of drainage line, backfilling and asphalt restoration.
Traffic Impacts:
- Robertson Boulevard will be closed between Venice Boulevard and Hoke Avenue.
- Northbound traffic on Robertson Boulevard will be detoured at Washington Boulevard to National Boulevard.
- Eastbound traffic on Venice Boulevard turning right onto southbound Robertson Boulevard will be detoured to National Boulevard.
- Westbound traffic on Venice Boulevard turning left onto southbound Robertson Boulevard will be detoured to Culver Boulevard.
- Local access to northbound Robertson Boulevard between Washington Boulevard and Hoke Avenue will be maintained by flaggers.
- Local access to all businesses will be maintained.
Advisories:
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Please do not enter the construction work zone and obey all posted construction signs.
- Electronic message boards and directional signage will be used to safely direct drivers and pedestrians around the construction zones.
- Local access to all businesses will be maintained
***Posted January 15, 2013
Please find enclosed an updated construction notice regarding utility work on National, Palms and Exposition Boulevards in the City of Los Angeles.
The relocation of existing on-street and underground utilities is necessary for construction of the National/Palms bridge structure and station. The work is being conducted by the Expo Line’s contractor on behalf of the Los Angeles Department of Water and Power. While closures and detours are necessary to conduct the work, the project has implemented a work plan to minimize the duration and impact to residents, businesses and commuters. We thank you for your patience as we build Phase 2 of the Expo Line project.
What: Relocation of On-Street and Underground Utilities
Where: Construction activities will take place at various points along National Boulevard, Palms Boulevard and Exposition Boulevard between Clarington Avenue and Tabor Street
Work Hours and Duration:
| Location | Work Hours | Duration (Revised) |
| Palms Boulevard (between Clarington and National Boulevard) | 9:00 a.m. – 3:30 p.m., Monday – Friday | Work will continue through March 22, 2013 |
| National Boulevard (between Clarington Avenue and Palms Boulevard) | 7:00 a.m. – 3:30 p.m., Monday – Friday | Work will continue through week of February 11, 2013 |
| Exposition Boulevard (between National Boulevard and Tabor Street) | 7:00 a.m. – 3:30 p.m., Monday – Friday | Work will continue through March 8, 2013 |
| Intersection of National Boulevard and Palms Boulevard (Full Closure) | 8:00 a.m. – 8:00 p.m., Saturday and Sunday | Work will take place on weekends between Saturday, January 26, 2013 and Sunday, March 10, 2013* |
* No work will take place during the Presidents Day Holiday weekend of February 16, 2013
Traffic Impacts:
- Palms Boulevard will be reduced to one lane of traffic in each direction between National Boulevard and Clarington Avenue intermittently during the work period.
- Westbound National Boulevard will be closed between Palms Boulevard and Clarington Avenue and all turns onto westbound National Boulevard will be prohibited. Eastbound National Boulevard will remain open.
- Exposition Boulevard between National/Palms Boulevard and Tabor Street will be closed to all through traffic intermittently during the work period. Westbound traffic will be detoured at Tabor Street and eastbound traffic will be detoured at Palms Boulevard.
- The intersection of National Boulevard and Palms Boulevard will be closed to all through traffic during the weekend closures. The detours for this closure are as follows:
- Eastbound traffic on National Boulevard will be detoured at Motor Avenue
- Northbound traffic on Palms Boulevard will be detoured at Motor Avenue
- Westbound traffic on National Boulevard will be detoured at Bagley Avenue
- Turns throughout the work area will be prohibited.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
- Electronic message boards, directional signage and/or flaggers will be used to maintain traffic flow and safely direct vehicles and pedestrians around the construction zone.
Advisories:
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
(Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.)
To view the construction notice – please click here.
***Posted January 14, 2013
In preparation for construction of Phase 2 of the Expo Light Rail Line, work crews will temporarily close National Boulevard between Manning Avenue and Exposition Boulevard for the installation of the falsework for the National/Palms Bridge in the City of Los Angeles. The work is being managed and performed by the Expo Phase 2 design-build contractor Skanska-Rados Joint Venture (SRJV), and its subcontractors.
What: Full Closure of National Boulevard for Falsework Installation for Bridge Construction
When: Monday, February 11, 2013 through Friday, February 22, 2013*
*Contingent upon approval
Work Hours: 9:00 p.m. to 6:00 a.m. Monday through Friday (Night work only)
Where: Construction activities will be located on National Boulevard north of the intersection of National/ Palms Boulevards
Work Description:
Construction crews will erect falsework using timber and steel forms as a mold for the cast-in-place concrete bridge that will span over National Boulevard.
Traffic Impacts:
? National Boulevard will be closed to all traffic between Manning Avenue and Exposition Boulevard throughout the falsework installation during nighttime hours.
? Westbound National Boulevard traffic will be detoured at Bagley Avenue.
? Northbound Palms Boulevard traffic will be detoured at Exposition Boulevard.
? All traffic lanes will be open to through traffic during daytime hours.
? Electronic message boards will be used to advise of the closures and manage traffic detours to update commuters as necessary.
? Directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
? Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
Advisories:
? Local access to businesses and residences will be maintained throughout all construction activities.
? Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
? Please obey all posted construction signs and do not enter the construction work zone.
(Construction schedules are subject to change for various reasons including but not limited to:
weather conditions, unforeseen emergencies and other acts of nature.)
***Posted November 25, 2012
What: Relocation of On-Street and Underground Utilities
Where: Construction activities will take place at various points along National Boulevard, Palms Boulevard and Exposition Boulevard between
Clarington Avenue and Tabor Street
Work Hours and Duration:
|
Location |
Work Hours |
Duration |
|
Palms Boulevard (between National Boulevard and Clarington Avenue) |
9:00 a.m. – 3:30 p.m., Monday – Friday |
Work will continue through January 31, 2013 |
|
National Boulevard (between Clarington Avenue and Palms Boulevard) |
7:00 a.m. – 3:30 p.m., Monday – Friday* |
December 1, 2012 – January 31, 2013 |
|
Exposition Boulevard (between Palms Boulevard and Tabor Street) |
7:00 a.m. – 3:30 p.m., Monday – Friday* |
December 1, 2012 – January 31, 2013 |
|
Intersection of National Boulevard and Palms Boulevard (Full Closure) |
8:00 a.m. – 8:00 p.m., Saturday and Sunday* |
4 consecutive weekends starting December 22, 2012 – January 13, 2013 |
* Hours contingent upon city approval
Work Description:
Construction activities will include removing and relocating existing on-street and underground utilities at various points along National Boulevard, Palms Boulevard and Exposition Boulevard. Major work activities will include setting and removing of traffic control devices, saw-cutting and removal of concrete and asphalt, excavation of soil, installation of shoring, vaults and new utilities, and backfill, concrete and asphalt replacement.
Traffic Impacts:
- Palms Boulevard will be intermittently reduced to one lane of traffic in each direction between National Boulevard and Clarington Avenue.
- National Boulevard will be intermittently reduced to one lane of traffic between Palms Boulevard and Clarington Avenue. Traffic in both directions will be maintained by flaggers.
- Exposition Boulevard between National/Palms Boulevard and Tabor Street will be intermittently closed to all through traffic. Westbound traffic will be detoured at Tabor Street and eastbound traffic will be detoured at Palms Boulevard.
- The intersection of National Boulevard and Palms Boulevard will be closed to all through traffic during 4 consecutive weekends. Southbound traffic on National Boulevard will be detoured at Manning Avenue; northbound traffic on Palms Boulevard will be detoured at Clarington Avenue; eastbound traffic on National Boulevard will be detoured at Clarington Avenue; and westbound traffic on Exposition Boulevard will be detoured at Watseka Avenue.
- Turns throughout the work area will be restricted as necessary.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
- Electronic message boards, directional signage and/or flaggers will be used to maintain traffic flow and safely direct vehicles and pedestrians around the construction zone.Advisories:
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
***Posted November 5, 2012
What: Relocation of On-Street and Underground Utilities
When: Wednesday, November 7, 2012 through Thursday, January 31, 2013
Work Hours: 9:00 a.m. to 3:30 p.m., Monday through Saturday
(No work will take place during the holidays)
Where: Construction activities will take place on Palms Boulevard between National Boulevard and Clarington Avenue
Work Description:
Construction activities will include removing and relocating existing on-street and underground utilities at various points along the Expo ROW on Palms Boulevard. Major work activities will include saw-cutting and removal of asphalt, excavation of soil, installation of new utilities, backfilling and asphalt restoration.
Traffic Impacts:
- Palms Boulevard will be reduced to one lane of traffic in each direction between National Boulevard and Clarington Avenue intermittently during the work period.
- Left turns through the work area will be prohibited intermittently during the work period.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
- Electronic message boards, directional signage and/or flaggers will be used to maintain traffic flow and safely direct vehicles and pedestrians around the construction zone.
Advisories:
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
***Posted November 3, 2012
What: Relocation of On-Street and Underground Utilities
When: Monday, November 5, 2012 through Friday, March 29, 2013
Work Hours: 7:00 a.m. to 3:30 p.m., Monday through Friday*
*Hours contingent upon city approval
Where: Construction activities will take place at the following locations:
- Sepulveda Boulevard from Pico Boulevard to Exposition Boulevard
- Exposition Boulevard from Sepulveda Boulevard, extending approximately 200 feet west of the intersection
Work Description:
Construction activities will include removing and relocating existing on-street and underground utilities at various points along Sepulveda and Exposition Boulevards. Major work activities will include saw-cutting and removal of asphalt, excavation of soil, installation of new utilities, backfilling and asphalt restoration.
Traffic Impacts:
- Sepulveda Boulevard will be reduced to one lane of traffic in each direction between Sepulveda Boulevard and Exposition Boulevard intermittently during the work period. Left turns through the work area will be restricted during the work period.
- Exposition Boulevard from Sepulveda Boulevard, extending approximately 200 feet west of the intersection will be reduced to one lane of traffic. Left turns onto westbound Sepulveda Boulevard will be restricted intermittently during the work period. Traffic in both directions will be maintained by flaggers.
- Parking restrictions on Sepulveda and Exposition Boulevards will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
- Electronic message boards, directional signage and/or flaggers will be used to maintain traffic flow and safely direct vehicles and pedestrians around the construction zone.
Advisories:
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Please obey all posted construction signs and do not enter the construction work zone.
***Posted October 25, 2012
What: Relocation of Water Line
When: Week of October 29, 2012 through Friday, December 14, 2012
Work Hours: Daytime: 9:00 a.m. to 3:30 p.m., Monday through Friday
Nighttime: 9:00 p.m. to 6:00 a.m., Monday through Friday
(No work will take place on weekends)
Where: Work will take place on the southbound lanes on Barrington Avenue at Exposition Boulevard
Work Description:
Water line relocation activities will include the relocation and replacement of the existing line. Daytime work activities will include saw cutting, asphalt removal, and compacting to restore the street. Nighttime work activities will include excavation of soil, pipe installation, backfilling, and any necessary waterline interruptions. Heavy machinery will be used, including excavators/backhoes, front-end loaders, small bulldozers and trucks. The noise generated by these activities will be comparable to that of a garbage truck and is not continuous.
Traffic Impacts:
- Barrington Avenue southbound lanes will be closed intermittently during work hours, southbound traffic will be diverted to the center turn lane.
- No left turns will be permitted from northbound Barrington Avenue onto westbound Exposition Boulevard. Barrington Boulevard northbound lanes will remain open.
- Parking restrictions on Barrington Avenue may be required throughout the work activity. Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
- Directional signage will be used to safely direct drivers around the construction zones in order to minimize the disruption to traffic.
Advisories:
- Water service interruptions may be required and will be noticed 72 hours in advance of the interruption.
- Electronic message boards will be used to alert travelers of the closures.
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels and sound blankets will be installed if required to buffer any noise that may impact the surrounding community.
- Work crews will water down the work area to minimize dust, sweep streets of debris as needed, and monitor the air.
- Please obey all posted construction signs and do not enter the construction work zone.
**Posted October 10, 2012
When: Work Continuing through Sunday, November 11, 2012
Work Hours: 9:00 p.m. to 5:00 a.m., Sunday through Thursday
12:00 a.m. to 8:00 a.m., Fridays (Occasional as needed)
Starting October 21, 2012 Sunday Hours will be Noon to 5:00 a.m.
Where: Work activity will take place near the intersection of Venice Boulevard and Robertson Boulevard
Work Description:
Sanitary sewer relocation activities will include the excavation of approximately 200 linear feet along westbound Venice Boulevard, to install new pipes and manholes. Upon completion of the work, the street will be restored.
Traffic Impacts:
- Traffic will be impacted on Venice Boulevard between Durango Avenue and Ivy Street.
- Westbound traffic on Venice Boulevard will be reduced to one lane between Curtis Avenue and Culver Boulevard.
- Eastbound traffic on Venice Boulevard will be reduced to two lanes between Curtis Avenue and Robertson Boulevard.
- On northbound Robertson Boulevard, left turns will be prohibited onto Venice Boulevard.
- On southbound Robertson Boulevard right turns will be prohibited onto Venice Boulevard.
- On eastbound Venice Boulevard, left turns onto Robertson Boulevard will be prohibited.
- Pedestrian access will be maintained on the south side of Venice Boulevard.
- Pedestrian traffic on the north side of Venice Boulevard will be re-directed to the south side of Venice Boulevard between Robertson Boulevard and Culver Boulevard.
- Electronic message boards and directional signage will be used to safely direct drivers and pedestrians around the construction zones.
Local access to all businesses will be maintained.
Advisories:
- Steel plates will be used to maintain traffic during daytime hours.
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Please do not enter the construction work zone and obey all posted construction signs.
**Posted October 10, 2012
What: Relocation of Water Line
When: Monday, October 15, 2012 through Friday, November 30, 2012
Work Hours: 9:00 a.m. to 3:30 p.m., Monday through Friday
(No work will take place on weekends)
Where: Work will take place on Bagley Avenue between Exposition Boulevard and Harlow Avenue
Work Description:
Water line relocation activities will include the relocation and replacement of the existing line. Major work activities will include saw-cutting and removal of asphalt, excavation of soil, pipe installation, and backfilling and asphalt restoration. Heavy machinery will be used, including excavators/backhoes, front-end loaders, small bulldozers and trucks. The noise generated by these activities will be comparable to that of a garbage truck and is not continuous.
Traffic Impacts:
- Bagley Avenue will be reduced to one lane of traffic between Exposition Boulevard and Harlow Avenue intermittently during the work period. Traffic in both directions will be maintained by flaggers.
- Directional signage will be used to safely direct drivers around the construction zones in order to minimize the disruption to traffic.
Advisories:
- Water service interruptions may be required and will be noticed 72 hours in advance of the interruption.
- Electronic message boards will be used to alert travelers of the closures.
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels and sound blankets will be installed if required to buffer any noise that may impact the surrounding community.
- Work crews will water down the work area to minimize dust, sweep streets of debris as needed, and monitor the air quality.
- Please obey all posted construction signs and do not enter the construction work zone.
**Posted October 10, 2012
What: Relocation of Water Line
When: Monday, October 15, 2012 through Friday, November 16, 2012
Work Hours: 9:00 a.m. to 3:30 p.m., Monday through Friday
(No work will take place on weekends)
Where: Work will take place on the northbound lane on Westwood Boulevard between North and South Exposition Boulevards
Work Description:
Water line relocation activities will include the relocation and replacement of the existing line. Major work activities will include saw-cutting and removal of asphalt, excavation of soil, pipe installation, and backfilling and asphalt restoration. Heavy machinery will be used, including excavators/backhoes, front-end loaders, small bulldozers and trucks. The noise generated by these activities will be comparable to that of a garbage truck and is not continuous.
Traffic Impacts:
- Westwood Boulevard northbound lane will be closed intermittently and traffic will be diverted to the center turn lane.
- Westwood Boulevard southbound traffic lane will remain open.
- No left turns will be permitted from northbound Westwood Boulevard onto westbound South Exposition Boulevard.
- Directional signage will be used to safely direct drivers around the construction zones in order to minimize the disruption to traffic.
Advisories:
- Water service interruptions may be required and will be noticed 72 hours in advance of the interruption.
- Electronic message boards will be used to alert travelers of the closures.
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels and sound blankets will be installed if required to buffer any noise that may impact the surrounding community.
- Work crews will water down the work area to minimize dust, sweep streets of debris as needed, and monitor the air quality.
- Please obey all posted construction signs and do not enter the construction work zone.
**Posted September 27, 2012
What: Relocation of Water Line
When: Monday, October 1, 2012 through Friday, November 2, 2012
Work Hours: Day: 9:00 a.m. to 3:30 p.m., Monday through Friday
Night: 9:00 p.m. to 6:00 a.m. Monday through Friday
Where: Work will take place on the two southbound lanes on Overland Avenue between Exposition Boulevard and Northvale Road
Work Description:
Water line relocation activities will include the relocation and replacement of the existing line. Major work activities will include saw-cutting and removal of asphalt, excavation of soil, pipe installation, backfilling and asphalt restoration. Heavy machinery will be used, including excavators/backhoes, front-end loaders, small bulldozers and trucks. Saw cutting and compacting to restore the street will be done during daytime work hours. The noise generated by these activities will be comparable to that of a garbage truck and is not continuous.
Traffic Impacts:
- Southbound traffic on Overland Avenue between Exposition Boulevard and Northvale Road will be reduced to one lane during construction work hours.
- Left turns will be prohibited through this intersection. Right turns from southbound Overland Avenue onto westbound Exposition Boulevard will be prohibited.
- Electronic message boards will be used to alert travelers of the closures 72 hours in advance of the work start.
- Directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
Advisories:
- Water service interruptions may be required and will be noticed 72 hours in advance of the interruption.
- Please obey all posted construction signs and do not enter the construction work zone.
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels and sound blankets will be installed if required to buffer any noise that may impact the surrounding community.
- Work crews will water down the work area to minimize dust, sweep adjacent streets of debris as needed, and monitor the surrounding air quality.
———————–
**Posted August 25, 2012
What: National/Palms Boulevard Bridge Construction
Work Hours: 7:00 a.m. to 6:00 p.m., Monday through Friday
Where: Construction will take place on the Expo ROW
When: Work activities are scheduled as follows:
| Restriping of Traffic Lanes andK-rail (Concrete Barrier) Installation | Monday, August 27, 2012 - 9:00 p.m. to 3:00 a.m. |
| Traffic Signal Relocation andFinal Activation | Monday, August 27, 2012 - 11:00 p.m. to 6:00 a.m.Wednesday, August 29, 2012 – 9:00 a.m. to 3:00 p.m. |
| Bridge Construction Begins | Thursday, August 30, 2012 (Day Work – approximately 12 months) |
Work Description:
Construction of the National/Palms Boulevard Bridge will be implemented in stages. Initial stages will include the realignment and restriping of traffic lanes on National Boulevard between Exposition Boulevard and Manning Avenue. K-rail (concrete barriers) will be placed on National Boulevard and at the northeast and northwest corners of the intersection with Exposition Boulevard. Abutment excavation will take place directly behind the K-rail to prepare the area for bridge construction. All additional construction activities will be limited to areas behind the K-rail on the Expo ROW. The traffic signals at this intersection will be temporarily disabled during the relocation and the final activation. Traffic Control Officers will direct traffic during this period.
Traffic Impacts:
- National Boulevard will remain open to through traffic during the daytime construction activities.
- One traffic lane in each direction will be closed during the nighttime work on Monday, August 20.
- Once the K-Rail is in place:
· Southbound National Boulevard: The street will be reduced to one lane between Manning Avenue and Exposition Boulevard. North of Manning Avenue, traffic will begin to transition to one through lane, and the right lane will be designated for right turns only. South of Manning Avenue, the left turn pocket will be eliminated, prohibiting left turns onto eastbound Exposition Boulevard, as well as U-turns.
· Northbound National Boulevard will remain as two lanes. However, left turns from Palms Boulevard onto National Boulevard will be prohibited, as well as U-turns.
· Eastbound and Westbound Exposition Boulevard will have all lanes open without restrictions. However, trucks will not be allowed to make right turns from westbound Exposition Boulevard onto northbound National Boulevard.
- National Boulevard will be closed on five separate nights throughout the construction period. Supplemental notices and electronic message boards will be used to advise the public when the closures are scheduled.
- Pedestrian access under the existing National Boulevard bridge will be maintained on the east side of National Boulevard via a designated walkway installed by the contractor.
- Electronic message boards, directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
- Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
Advisories:
- Local access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
- Work crews will water down the work area to minimize dust, sweep adjacent streets of debris as needed, and the air will be monitored.
- Please obey all posted construction signs and do not enter the construction work zone.
———————
**Posted August 18, 2012
What: National/Palms Boulevard Bridge Construction
Work Hours: 7:00 a.m. to 6:00 p.m., Monday through Friday
Where: Construction will take place on the Expo ROW
When: Work activities are scheduled as follows:
Restriping of Traffic Lanes and
K-rail (Concrete Barrier) Installation
Monday, August 20, 2012 (Night Work) – 9:00 p.m. to 5:00 a.m.
Traffic Signal Relocation
Tuesday, August 21, 2012 (Day Work)
Bridge Construction Begins
Wednesday, August 22, 2012 (Day Work – approximately 12 months)
Work Description:
Construction of the National/Palms Boulevard Bridge will be implemented in stages. Initial stages will include the realignment and restriping of traffic lanes on National Boulevard between Exposition Boulevard and Manning Avenue. K-rail (concrete barriers) will be placed on National Boulevard and at the northeast and northwest corners of the intersection with Exposition Boulevard. Abutment excavation will take place directly behind the K-rail to prepare the area for bridge construction. All additional construction activities will be limited to areas behind the K-rail on the Expo ROW.
Traffic Impacts:
National Boulevard will remain open to through traffic during the daytime construction activities.
One traffic lane in each direction will be closed during the nighttime work on Monday, August 20.
Once the K-Rail is in place:
· Southbound National Boulevard: The street will be reduced to one lane between Manning Avenue and Exposition Boulevard. North of Manning Avenue, traffic will begin to transition to one through lane, and the right lane will be designated for right turns only. South of Manning Avenue, the left turn pocket will be eliminated, prohibiting left turns onto eastbound Exposition Boulevard, as well as U-turns.
· Northbound National Boulevard will remain as two lanes. However, left turns from Palms Boulevard onto National Boulevard will be prohibited, as well as U-turns.
· Eastbound and Westbound Exposition Boulevard will have all lanes open without restrictions. However, trucks will not be allowed to make right turns from westbound Exposition Boulevard onto northbound National Boulevard.
National Boulevard will be closed on five separate nights throughout the construction period. Supplemental notices and electronic message boards will be used to advise the public when the closures are scheduled.
Pedestrian access under the existing National Boulevard bridge will be maintained on the east side of National Boulevard via a designated walkway installed by the contractor.
Electronic message boards, directional signage and/or flagmen will be used to safely direct vehicles and pedestrians around the construction zone.
Parking restrictions will be strictly enforced at all times and signage with specific restrictions will be in place in all construction areas.
Advisories:
· Local access to businesses and residences will be maintained throughout all construction activities.
· Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
· Work crews will water down the work area to minimize dust, sweep adjacent streets of debris as needed, and the air will be monitored.
· Please obey all posted construction signs and do not enter the construction work zone.
——————-
**Posted August 3rd, 2012
When: Thursday, August 2, 2012 through Friday, September 21, 2012
Work Hours: 9:00 p.m. to 5:00 a.m., Sunday through Thursday
12:00 a.m. to 8:00 a.m., Fridays (Occasional as needed)
Where: Work activity will take place near the intersection of Venice Boulevard and Robertson Boulevard
Work Description:
Sanitary sewer relocation activities will include the excavation of approximately 200 linear feet along westbound Venice Boulevard, to install new pipes and manholes. Upon completion of the work, the street will be restored.
Traffic Impacts:
- Traffic will be impacted on Venice Boulevard between Durango Avenue and Ivy Street.
- Westbound traffic on Venice Boulevard will be reduced to one lane between Curtis Avenue and Culver Boulevard.
- Eastbound traffic on Venice Boulevard will be reduced to two lanes between Curtis Avenue and Robertson Boulevard.
- On northbound Robertson Boulevard, left turns will be prohibited onto
Venice Boulevard.
- On southbound Robertson Boulevard right turns will be prohibited onto Venice Boulevard.
- On eastbound Venice Boulevard, left turns onto Robertson Boulevard will be prohibited.
- Pedestrian access will be maintained on the south side of Venice Boulevard.
- Pedestrian traffic on the north side of Venice Boulevard will be re-directed to the south side of Venice Boulevard between Robertson Boulevard and
Culver Boulevard.
- Electronic message boards and directional signage will be used to safely direct drivers and pedestrians around the construction zones.
- Local access to all businesses will be maintained.
;
Advisories:
- Steel plates will be used to maintain traffic during daytime hours.
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Please do not enter the construction work zone and obey all posted construction signs.
—————-
**Posted July 27, 2012**
What: Inspection and reinforcement of Sanitary Sewer Encasements
When: Monday, July 30 through Friday, August 24, 2012 (No work will take place on weekends)
Work Hours: 9:00 a.m. to 3:30 p.m., Monday through Friday
Where: Work will take place on the center turn lane and the two adjacent lanes on Overland Avenue between Exposition Boulevard and Northvale Road
Work Description:
Excavation will take place on the center turn lane and the two adjacent lanes on Overland Avenue to inspect the existing sewer line. Heavy machinery will be used for the sewer inspection and upgrade, including excavators/backhoes, front-end loaders, small bulldozers and trucks. Compacting equipment will be used to compact and restore the street. The noise generated by these activities will be comparable to that of a garbage truck and is not continuous.
Traffic Impacts:
- The center turn lane and the two adjacent lanes on Overland Avenue between Exposition Boulevard and Northvale Road will remain closed during construction work hours. Left turns will be prohibited at this intersection.
- Electronic message boards will be used to alert travelers of the closures 72 hours in advance of the work start.
- Directional signage will be used to safely direct drivers around the construction zones in order to minimize the disruption to traffic.
Advisories:
- Please obey all posted construction signs and do not enter the construction work zone.
- Access to businesses and residences will be maintained throughout all construction activities.
- Noise levels will be monitored to ensure work performed is within the necessary compliance levels and sound blankets will be installed if required to buffer any noise that may impact the surrounding community.
- Work crews will water down the work area to minimize dust, sweep adjacent streets of debris as needed, and the air will be monitored.
————————-
**Posted July 17 2012**
What: Closed Camera Television (CCTV) Inspection of Sanitary Sewer Encasement
When: Wednesday, July 18, 2012
Work Hours: 12:00 p.m. to 3:30 p.m.
Where: Work will take place on the center turn lane and the two adjacent lanes on Overland Avenue between Exposition Boulevard and Northvale Road
Work Description:
A video inspection of the current sewer line encasement condition will be performed before excavation and concrete encasement work continues on Overland Avenue. Work will take approximately 3.5 hours. The video inspection will be conducted using a Closed Circuit Television Camera (CCTV).
Traffic Impacts:
- The center turn lane and the two adjacent lanes on Overland Avenue between Exposition Boulevard and Northvale Road will remain closed during construction work hours.
- Left turns at this intersection will be prohibited at this intersection during work hours.
- Electronic message boards will be used to alert travelers of the closures.
- Directional signage will be used to safely direct drivers around the construction zones in order to minimize the disruption to traffic.
Advisories:
- Access to businesses and residences will be maintained throughout all construction activities.
- Please obey all posted construction signs and do not enter the construction work zone.
(Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.)
————
**Posted July 12, 2012**
What: Soil removal and grading necessary for the start of construction
When: Monday, July 23, 2012 through Friday, September 28, 2012
Work Hours:
- 7:00 a.m. to 6:00 p.m., Monday through Friday in the City of Los Angeles
- 8:00 a.m. to 6:00 p.m., Monday through Friday in the City of Santa Monica
- No work will take place on weekends
Where: Work will take place within the Expo ROW, throughout the alignment between Bagley Avenue in the City of Los Angeles and 17th Street in the City of Santa Monica
Work Description:
Construction crews will continue soil removal and grading within the right-of-way. Equipment used for these construction activities will include: excavators, compaction rollers, front-end loaders, backhoe loaders, bulldozers and trucks. Work crews will perform excavations under local, state and federal regulations and in a manner that does not harm the public or the environment. The California Department of Toxic Substances Control (DTSC) will oversee this process and ensure that it is performed accordingly.
Advisories/Mitigation Measures:
- Dust Control - The following measures will be implemented to prevent fugitive dust from leaving the site: the use of watering trucks to wet the soil, covering truck loads with tarps before they leave the work site, and the designation of a specific entrance and exit for all equipment and trucks hauling debris where an anti-soil tracking device will be installed. Additionally, street sweepers will be used to keep clear the streets of debris as needed.
- Soil Sampling and Analysis - In 2010, the soil in the Expo ROW was sampled for soil contaminants. Arsenic, lead, petroleum hydrocarbons, polychlorinated biphenyls, polycyclic aromatic hydrocarbons, and volatile organic compounds were found at various locations and depths below the ground surface in the Expo ROW. There is no immediate health risk to the residents or businesses in the area; however, DTSC recommended that the contaminated soil be removed to prevent the potential for future exposure.
- California Department of Toxic Substances Control (DTSC) – is responsible for the oversight of the soil removal process to ensure that the Expo Authority and its contractor, SRJV and their subcontractors perform the excavations under local, state, and federal regulations. All necessary precautions will be implemented to make certain that site workers and the community are safe during the soil removal activities. If you have questions or would like more information, please contact the Expo Construction Authority or DTSC. You may contact: Yvette LaDuke, Public Participation Specialist, at 818-717-6569 or via email:yladuke@dtsc.ca.gov or the AQMD Complaint Hotline at (909)288-7664.
Traffic Impacts/Access:
- Trucks used to haul away debris will occasionally interrupt traffic as they enter and exit the ROW; however, flagmen will be used to safely direct drivers to minimize traffic disruptions.
- Access to businesses and residences will be maintained throughout all construction activities.
- Please obey all posted parking restriction signs and construction signs; do not enter the construction work zone.
————————-
**Posted June 13, 2012**
What: Sewer Investigation and Relocation of Sanitary Sewer Line
When: Monday, June 18, 2012 through Friday, September 21, 2012
Work Hours: 9:00 p.m. to 5:00 a.m., Monday through Thursday
12:00 a.m. to 5:00 a.m., Fridays (No work will take place on weekends)
———————
Posted June 13, 2012
Where: Work activity will take place near the intersection of Venice Boulevard and Robertson Boulevard
Work Description: Sewer investigation activities will take place the week of June 18th. Sanitary sewer relocation activities will follow and will include the excavation of approximately 200 linear feet along westbound Venice Boulevard, to install new pipes and manholes. Upon completion of the work, the street will be restored.
Traffic Impacts:
- Traffic will be impacted on Venice Blvd. between Durango Ave. and Ivy St.
- Westbound traffic on Venice Blvd. will be reduced to one lane between Curtis Ave. and Culver Blvd.
- Eastbound traffic on Venice Blvd. will be reduced to two lanes between Curtis Ave. and Robertson Blvd.
- On northbound Robertson Blvd., left turns will be prohibited onto Venice Blvd.
- On southbound Robertson Blvd., right turns will be prohibited onto Venice Blvd.
- On eastbound Venice Blvd., left turns onto Robertson Blvd. will be prohibited.
- Pedestrian access will be maintained on the south side of Venice Blvd.
- Pedestrian traffic on the north side of Venice Blvd. will be re-directed to the south side of Venice Blvd. between Robertson Blvd. and Culver Blvd.
- Electronic message boards and directional signage will be used to safely direct drivers and pedestrians around the construction zones.
- Local access to all businesses will be maintained.
Advisories:
- Steel plates will be used to maintain traffic during daytime hours. .
- Parking and “No Stopping Anytime” restrictions will be strictly enforced at all times.
- Please do not enter the construction work zone and obey all posted construction signs.